【9/17 (Tue)】A connected water pipe withstand pressure test Integrated Research Bldg. and GSID Bldg.
Dear GSID All,
At Integrated Research Bldg. and GSID Bldg., a connected water pipe withstand pressure test for a fire equipment inspection will be conducted on the following schedule.
Tuesday, September 17
・Integrated Research Bldg.: Starts around 9:00 a.m.
・ GSID Bldg.: Starts as soon as Integrated Research Bldg finishes.
*The working time is expected to be around 2 hours per place.
*The work will be done outside and on the roof, so there will be no entry into each room.
*There is no alarm such as an emergency bell.
The outdoor work will be around the entrance.
We apologize for the inconvenience and thank you for your understanding.
[Contact]
Facilities Management Department.